Exhaust systems were required to serve 2 No existing Mitsubishi 1150 KW generators and 1 No new 1000 KW generator installed at the Mount Pleasant Royal Mail Sorting Office.
2 No 450mm ID and 1 No 350mm ID stainless steel twin wall insulated exhaust systems were installed in 2 separate phases. The vertical risers for all 3 systems were installed in the first phase in a triangular formation using specially designed brackets. The horizontal sections were installed in the second phase.
Have a question about this project?
Contact UsClient: | Imtech |
Project: | Design & install new generator exhaust systems |
Services: | System Design, Project Management, Installation |
Duration: | 18 months |